Project Schedule:

  • Planning and design began in 2002 and is expected to be complete in 2009.
  • Next steps include property acquisition, final project approval and contract bidding. 
  • Project construction is expected to commence in the late fall of 2009 and will take 8 to 10 months to complete.

 

 View an illustration of the planned 30th Street transportation improvements

 View the Project Fact Sheet

 View July 2, 2009 Weekly Information Packet (including the story of 30th St) memorandum to City Council

 

Upcoming Public Meetings: (see EVENTS)

  • August 3, 2009 Design Charrette

  • August 4, 2009 Agenda Item on City Council Meeting

Previous Public Meetings: